Connecting to our Network

Note: This leaflet is to be used as a guide only. There may be other conditions applicable. Please contact WEL Networks limited on (07) 850 3100 if you have any queries.

HOW A CUSTOMER CONNECTS TO THE WEL Network
 
Choose an electricity retailer

Fill out the chosen Electricity Retailer's, and WEL's application forms, and return them both to your chosen Retailer.

 
WEL advises electrical contractors of application for connection approval.
 
The customer's Electrical Contractor advises WEL that installation is ready to connect
 
WEL connects the customer


New connections - the processs


SHARING THE RESPONSIBILITIES

CUSTOMERS RESPONSIBILITIES

  • The customer must furnish a completed Application for Connection.
    (Refer Page 3)
  • The customer must have a contract with an Energy Retailer.

WEL NETWORKS RESPONSIBILITIES

  • WEL is responsible for providing an appropriate supply in tems of voltage, connection, polarity and correct fusing to suit the connection up to the Network Connection Point (NCP)

ELECTRICIAN'S RESPONSIBILITIES

  • For the service-main and installation construction. (Refer Page 4)
  • Sizing of the service-main to suit demand and voltage criteria.
  • Provision of metering space for the Energy Retailer.
  • Provision of a Certificate of Compliance for the service-main and the installation.

ELECTRICITY RETAILER RESPONSIBILITIES

  • To provide and install metering.
  • To receive and pay the Network Charges.
  • To provide ongoing customer service.
  • To send the bill to the customer for total electricity supplied.


NETWORK CONNECTION STANDARD (DISTRIBUTION CODE)

Click here to view the Network Connection Standard (Distribution Code) effective 1 May 2009


HOW TO APPLY FOR A NEW CONNECTION

  1. Applications are required for all new connections, alterations, temporary connections and permanent disconnections and must be lodged using the Application form. Application forms are available on the WEL Networks Web site (www.wel.co.nz) or from the Electricity Retailer.
  2. On the forms all customers panels must be filled in completely and with adequate details to enable WEL to process the application.
  3. It is vital that complete site information is provided in order to locate exactly where the connection is required.
  4. If inadequate information is received, applications may be returned which will result in delays.
  5. It is important to estimate accurately the maximum demand in kW and record in the space provided on the application form. This should reflect the actual demand and not the calculated listed equipment load. Diversity should be allowed for.

Allow 15 working days for WEL to approve your connection.


HOW TO GET THE SERVICE-MAINS CONNECTED

  1. The installing electrician will need to advise WEL at least 5 working days before the mains are ready to be connected to WEL's network.
  2. It may take up to 15 working days to obtain consents from councils and obstruction clearances from other underground service utilities before trenching can begin in respect of connections that require trenching in the road reserve.

LIVENING THE INSTALLATION

  1. Only when the service-main is connected, the metering installed, all WEL endorsements complied with and the electrical compliance completed, the installation will be livened.
  2. WEL may be advised when the installation is ready to liven by either the electrician or the electrical retailer. If WEL is aware that livening is required and that all matters are in place, WEL will forward livening instructions to their authorised contractor.
  3. Only a WEL authorised contractor can work on WEL's network.
  4. WEL will advise the customer and the Electricity Retailer that the installation has been livened.


TEMPORARY CONNECTIONS, ALTERATIONS AND DISCONNECTIONS SPECIFIC INFORMATION

Temporary connections

  1. WEL can not guarantee that a supply will be available for temporary connections. You will be advised in writing if WEL does not have a Network Connection Point (NCP) available.
  2. If a NCP is required for a permanent connection and WEL does not have reticulation near the site, planning for establishing an NCP can be made at the temporary connection stage.
  3. All costs to connect and establish a temporary connection are payable by the person making the request.

Alterations to a Network Supply

An application for an increased load must be submittedin the following circumstances:

    • An increase in the number of phases (e.g. single phase to three phase)
    • An increase in the required connection fuse rating (e.g. 60A to 100A)
    • Any additional meter and/or controlled load/relay
    • Any significant increase in load within the existing connected fuse rating

Similarly a decreased load application must be submitted if the reverse is true.

Permanent Disconnections

Situations that require a disconnection of service-mains are: - demolitions, building removals and site alterations.

Adequate time should be allowed in order for WEL to organise the disconnection. WEL must receive confirmation from the customer's Electricity Retailer before permanent disconnection can proceed.


Last updated: Monday, 19 October 2009

 

Latest News

WEL NETWORKS & PARTNERS SELECTED TO ENTER NEGOTIATIONS FOR FIRST STAGE UFB ROLLOUT
Media Release 9 September 2010   WEL Networks & Partners Selected to Enter Negotiations... more...
ENERGY EFFICIENCY: DO WAIKATO SCHOOLS MAKE THE GRADE?
WEL Networks is looking to do its part to help Waikato school children keep warm and dry in... more...
WEL NETWORKS SEEKS CUSTOMERS TO TEST NEW ELECTRICITY TECHNOLOGIES
WEL Networks is seeking customers willing to work with the company to test new electricity... more...
WEL Networks Update
WEL Networks Customer Newsletter Issue One April 2010 To view the newsletter either click here... more...
RESIGNATION OF CHAIRPERSON - WEL ENERGY TRUST
Issued by WEL Energy Trust     18 January 2010     News Release       WEL Energy Trust... more...