Subdivisions

THE PROCESS

Subdivision development will require the developer to install all necessary reticulation to the individual lots.   If you are subdividing in the WEL Networks area (refer to Area Map) you will need to make arrangements to connect to our network.


1. Forward proposed subdivision plan for design

To enable WEL to complete a design for your proposed subdivision please forward a copy of your proposed subdivision plan (for rural subdivisions preferably with proposed house sites shown), an indication of when installation will be required and any special requirements you may have. 

This can be either by post (PO Box 925, Hamilton Attention: Desig and Construction) or by email to supply@wel.co.nz.


2. Design carried out and priced

Upon receipt of your plan we will complete the design to install electrical reticulation to the proposed new lots and price the works required. This process may take between 2-4 weeks.


3. Quotation sent to Developer advising of works required and costs

The developer will be required to contribute towards the cost of the installation.  The amount of contribution will depend on the cost of the work and the size and location of the development.

In addition there may be an additional Development Fee.  This fee is a capital contribution towards the cost of upgrading the local electrical network. This means that existing customers do not subsidise the additional costs of connecting new developments while ensuring that everyone receives the benefits of the network which the community has built up over a number of years.

In the urban areas of Hamilton, Raglan, Ngaruawhia, Huntly & Te Kauwhata the volume of recent new connections requires significant work to be done to upgrade the local network in order to support the increased electrical load. WEL Networks currently require a capital contribution of $1,000 + GST for each new connection made in this area to spread the cost of this work over the customers who will benefit from it. This contribution is in addition to the direct cost of connecting new properties to the network.

The developer will be required to make payment prior to works proceeding. 

 

4. Developer accepts quotation and works undertaken

Upon acceptance of the quotation by the Developer the installation works will be programmed into be completed.  The time frame for this will depend on the developers' construction programme and WEL's current commitments, allow at least 4-6 weeks from acceptance/payment of quotation.

Construction of this nature does have 'peak periods', can be weather dependent and in some instances there will be lead times required for some materials.   Good communication between the Developer and WEL Project Manager will be crucial to ensure the project proceeds to plan.

5. Works completed and Completion letter sent

When the works have been completed please contact us to request a completion letter to be sent.   This states that you have met the necessary Council requirements for the installation of power to your subdivision.               
 


FREQUENTLY ASKED QUESTIONS

Can you give me an indication of cost for my subdivision?
 
As I have paid for my subdivision reticulation why do I have to pass ownership to WEL?
 
My local electrical contractor can lay cable in ground cheaper than WEL can. Is there any problem in using him?
 
I still want to own the reticulation that I have installed on my new subdivision. Can I do this?

Why are easements required?


Can you give me an indication of cost for my subdivision?
 
Unfortunately due to the number of variables including the terrain, existing reticulation etc, we can not give an indication of cost until a site visit is conducted.


As I have paid for my subdivision reticulation why do I have to pass ownership to WEL?
 
Once WEL has ownership of any new reticulation we take permanent responsibility for managing, controlling and maintaining the reticulation.


My local electrical contractor can lay cable in ground cheaper than WEL can. Is there any problem in using him?
 
WEL have a legal responsibility to ensure the safety of electrical reticulation that will form part of our network. We also need to ensure that all electrical reticulation is installed to specified standards so that we can provide a reliable service to customers. We therefore require installation contractors to be certified to work on our network.
 
Where contractors are certified to work on our network we still need to manage the installation process to ensure the ongoing quality and safety of the reticulation installed. This also requires us to ensure that all new reticulation is recorded correctly on our networks plans and control systems.


I still want to own the reticulation that I have installed on my new subdivision. Can I do this?

In theory, yes. 
 
Assuming that the reticulation has been installed to meet industry standards then WEL can connect the new reticulation at the boundary of the subdivision. You will however need to make appropriate arrangements for managing the network including providing fault response services, entering into contracts with energy retailers for the use of your network and appointing a competent person to oversee the safe operation of the network. You will also have to pay for the supply, installation and monitoring of reconciliation metering at the point of connection.


Why are easements required?

Easements are necessary because WEL needs to ensure it can have legal access to maintain and upgrade its cables / lines.
There are several scenarios where easements will be required:

  • Where there are existing WEL Network lines/cable crossing a property to which the new subdivision may or may not be connected.
  • Where the existing service line(s) to the existing dwelling etc cross over a new lot
  • Where new cabling or lines are installed in private property (including right of ways) to supply the new lots.

     
     

Last updated: Thursday, 20 May 2010

 

Latest News

ENERGY EFFICIENCY: DO WAIKATO SCHOOLS MAKE THE GRADE?
WEL Networks is looking to do its part to help Waikato school children keep warm and dry in... more...
WEL NETWORKS SEEKS CUSTOMERS TO TEST NEW ELECTRICITY TECHNOLOGIES
WEL Networks is seeking customers willing to work with the company to test new electricity... more...
WEL Networks Update
WEL Networks Customer Newsletter Issue One April 2010 To view the newsletter either click here... more...
RESIGNATION OF CHAIRPERSON - WEL ENERGY TRUST
Issued by WEL Energy Trust     18 January 2010     News Release       WEL Energy Trust... more...
ELECTRICITY TRANSMISSION ROUTE FROM TE UKU WIND FARM FINALISED
MEDIA RELEASE   WEL Networks announced today that it has finalised plans for its... more...