You'll need:
Your electrical requirements (number of phases, fuse size). If you have it, a site plan can also be provided.
Your electrician can provide these details.
It depends on the complexity of your new connection but if the application is for a Standard Connection as per Capital Contribution Policy you can expect your fixed price quote within five working days.
WEL'sFor non-standard connections it may take between six to eight weeks to provide your fixed price quote. This allows time for the design to be completed and a quote to be issued. This timeframe will vary if an easement is required. Will I require an easement?
Providing all relevant information at the start of the process will help ensure it is as efficient as possible.
Typically we do not charge an application fee for Standard Connection Applications, but we may ask you to pay a non-refundable application deposit for Non-Standard Connections. To find out more contact WEL Networks.